Mumbai-Ahmedabad Bullet Train Stations Rapidly Taking Shape in Gujarat

Published Date

Rail Level Slab of Five Bullet Train Stations (Vapi, Bilimora, Surat, Anand and Ahmedabad) is completed

Mumbai-Ahmedabad Bullet Train corridor will dot 12 stations along the alignment of 508 kms. Gujarat will have eight (08) stations starting from Sabarmati, Ahmedabad, Anand, Vadodara, Bharuch, Surat, Bilimora and Vapi and four (04) in Maharashtra i.e. Boisar, Virar, Thane and Mumbai.

The construction work on Bullet Train stations all along the alignment are progressing rapidly. The foundation work on all 8 stations in Gujarat is completed and the construction of superstructures is at an advanced stage. 

The stations on the corridor will have all modern and advanced facilities and amenities for passengers. There will be ticketing and waiting areas, business-class lounge, nursery, restrooms, smoking rooms, information booths, retail centres and public information and announcement system. Moreover, some stations will be developed as a transport hub through integration with all basic modes of transportation for better, faster and hassle-free connectivity to and from the station, such as autos, buses and taxis.

Progress of Stations in Gujarat

Bullet Train Station Concourse Level Slab Rail Level Slab Remarks
Vapi 425 m 425 m Completed
Bilimora 425 m 425 m Completed
Surat 450 m 450 m Completed
Bharuch 425 m 425 m Out of 425 m, 350 m is completed
Vadodara 425 m 425 m Casting of first floor slab work in progress
Anand 425 m 425 m Completed
Ahmedabad 435 m 435 m Completed
Sabarmati 425 m 425 m First floor: All 9 slabs completed
Concourse: Out of 9 slabs, 3 are completed

 