National High Speed Rail Corporation Limited (NHSRCL) marks the completion of 100% land acquisition in the state of Gujarat for Mumbai-Ahmedabad High Speed Rail Corridor project.
Total land required for the project in Gujarat: 951.14 Hectares
Number of districts: 8
The last parcel of land in Gujarat was acquired at Kathore village of Surat district (4.99 Ha) in the month of September 2023.
District wise land acquisition in Gujarat
(Area in Ha) | No. of Pvt. Plots | ||
---|---|---|---|
District | Scope | Acquisition | |
Ahmedabad | 133.29 | 133.29 | 140 |
Kheda | 110.25 | 110.25 | 803 |
Anand | 52.59 | 52.59 | 546 |
Vadodara | 142.30 | 142.30 | 919 |
Bharuch | 140.32 | 140.32 | 1057 |
Surat | 160.51 | 160.51 | 997 |
Navsari | 88.93 | 88.93 | 748 |
Valsad | 122.95 | 122.95 | 1126 |
Total (B) | 951.14 | 951.14 (100%) | 6336 |
Land Acquisition Status for MAHSR Project
Total land required for the project: 1389.49 Ha
Overall: - 99.95 % (1388.75 Ha)
Gujarat: - 100 % (951.14 Ha)
DNH: - 100 % (7.90 Ha)
Maharashtra: - 99.83 % (429.71 Ha)