• Total length of Mainline : 135.45 Km (Between Shilphata & Zaroli village on Maharashtra -Gujarat Border)
• Viaduct & Bridges: 124.027 km
• Earth Structure: 5.361 km
• Bridges & Crossings: 36 Nos. including 12 steel bridges
• Stations: 3 nos. namely Thane, Virar & Boisar
• Mountain tunnels: 6 nos. & 1 no. cut & cover tunnel
• Main River Bridges: Ulhas River, Vaitarna & Jagani
Current status of work
• Geotechnical investigation for the complete 135 km is nearing completion with major locations like Vaitarna River, Virar & Boisar bullet train station already completed
• Work on two of the mountain tunnels has also commenced in this region
• Pier foundation work has commenced at multiple locations
• Casting yards are being developed for full span and segment casting of girders