Media Brief on Completion of 100 Kms of Pier Work on MAHSR Corridor

Published Date

Completion of 100 Kms of Pier Work on MAHSR Corridor

Mumbai-Ahmedabad High Speed Rail Corridor has achieved a milestone of completing 100 kms of pier work in the state of Gujarat (352 Kms).

Other details are as follows:

  1. Project Update in Gujarat State
    • Piers have been constructed over a stretch of 100 km
    • Pile has been cast over a length of 193 km
    • 9.2 km of viaduct is completed which includes 2.5 km of continuous viaduct near Navsari and 6.7 km erected at different locations.
    • Girder Casting – 22.7 km girders have been cast and 9.2 km girders have been erected.
    • Construction work have started in full swing all along the alignment passing through 8 districts of Gujarat & DNH.
    • The works on 8 HSR Stations from Vapi to Sabarmati are under various stages of construction.
    • Bridge Works on important rivers viz., Narmada, Tapti, Mahi and Sabarmati is in progress.
  2. Land Acquisition Status:
    • Overall:- 97.82%
    • Gujarat:- 98.87%
    • DNH:- 100%
    • Maharashtra:- 95.45%

Status of Possession of Land in Maharashtra is 73.83 %