Launching of 45m Long SBS Span and Passing of Full Span Girder at Petlad Canal for Mumbai-Ahmedabad High Speed Rail Corridor

Published Date

Salient Features

  • MAHSR viaduct crossed over Petlad Canal (irrigation canal of Mahi river), Anand District, Gujarat
  • As Full Span Launching Method (FSLM) was not possible, Span By Span (SBS) method was used
  • Water flow was not obstructed during the construction phase
  • 19 segments were joined to make 45 m span over the canal
  • 1000 MT Full Span Girder was moved over the SBS span to complete the construction