Media Brief : 100% land acquisition in Gujarat for MAHSR project

Published Date

National High Speed Rail Corporation Limited (NHSRCL) marks the completion of 100% land acquisition in the state of Gujarat for Mumbai-Ahmedabad High Speed Rail Corridor project.

Total land required for the project in Gujarat: 951.14 Hectares
Number of districts: 8

The last parcel of land in Gujarat was acquired at Kathore village of Surat district (4.99 Ha) in the month of September 2023.

District wise land acquisition in Gujarat

(Area in Ha) No. of Pvt. Plots
District Scope Acquisition
Ahmedabad 133.29 133.29 140
Kheda 110.25 110.25 803
Anand 52.59 52.59 546
Vadodara 142.30 142.30 919
Bharuch 140.32 140.32 1057
Surat 160.51 160.51 997
Navsari 88.93 88.93 748
Valsad 122.95 122.95 1126
Total (B) 951.14 951.14 (100%) 6336

Land Acquisition Status for MAHSR Project

Total land required for the project: 1389.49 Ha

Overall: - 99.95 % (1388.75 Ha)

Gujarat: - 100 % (951.14 Ha)

DNH: - 100 % (7.90 Ha)

Maharashtra: - 99.83 % (429.71 Ha)