A 210 m long PSC (Pre-stressed concrete) bridge designed to cross over National Highway-48 (Delhi-Chennai) at Dabhan village, near Nadiad, Kheda district, Gujarat is completed on 9th January 2025.

The bridge comprises of 72 precast segments with four spans of configuration 40m + 65m + 65m + 40m and was built using  Balanced Cantilever Method, which is ideal for larger spans. This newly completed bridge is situated between Anand and Ahmedabad Bullet Train stations.

Details of completed bridges on NH-48

Sr. No. Length of the bridge
(in meters)
Span Configuration Bullet Train Stations District Completed On
4th PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Anand & Ahmedabad Kheda 9th January 2025
3rd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Vapi & Bilimora Valsad 2nd January 2025
2nd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Surat & Bilimora Navsari 1st October 2024
1st PSC Bridge 260 Four spans of configuration 50m + 80m + 80m + 50m Between Surat & Bilimora Navsari 18th August 2024


Project status as on 11th Jan 2025
•    253 km of viaduct, 290 km of girder casting and 358 km of pier work completed
•    Bridges on 13 rivers and five steel bridges completed
•    Noise barriers have been installed over a stretch of approx. 112 km
•    Track construction work has commenced at multiple locations in Gujarat
•    The work on 21 km tunnel between BKC and Thane in Maharashtra is under construction.
•    Seven mountain tunnels are under construction in Palghar district, Maharashtra through NATM. One mountain tunnel in Valsad district, Gujarat is already completed