Salient Features of Mumbai-Ahmedabad High Speed Rail Corridor
- Total length of the corridor: 508.17 KM
- Maximum Operational Speed: 320 Kmph
- Time Taken:
o 2.07 hours (limited stops)
o 2.58 hours (all stops)
- Total number of Stations: 12
o Gujarat: 8
o Maharashtra: 4
- Stations in Gujarat: Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad and Sabarmati
- Stations in Maharashtra: Mumbai (BKC), Thane, Virar and Boisar
- Number of Depots: 3
o Gujarat: 2 (Surat & Sabarmati)
o Maharashtra: 1 (Thane)
- Operational Control Center: Sabarmati
- Land Acquisition Status:
Gujarat: Already Acquired 98.81%
Dadra Nagar Haveli: 100%
Maharashtra: Already Acquired – 72.25% (Pvt.-92.8%; Govt.-92.28%; Forest-Nil)
Project Update in Gujarat State and DNH
• In Gujarat and Dadra & Nagar Haveli, 100% of Civil and Track contracts for construction of the route i.e. 352 Kms have been awarded to Indian Contractors.
• The works on Piles, Foundations, Piers, Pier Caps, casting & erection of Girders for Viaduct & Stations have started in full swing along the alignment passing through 8 districts of Gujarat.
• Construction work of Piles, Pile Caps, Open Foundations, Well Foundations, Piers, Pier Caps is in progress in 180 km length.
• Viaduct - Substructure: Till date, 157.8 km Piling, 88.4 km Foundation and 75.1 km Pier work has been completed
• Special Bridges:
Crossings over National & State Highways, Irrigation Canals and Railways, will be bridged by long span Steel structures. Test Fabrication has been completed in 4 workshops and actual fabrication is in progress.
Bridge Works on important rivers viz., Narmada, Tapti, Mahi and Sabarmati is in progress. Status is tabulated below:
| Narmada Bridge | Out of 22, work is in progress on 15 Well foundations |
| Mahi Bridge | Work is in progress on all 12 Well foundations |
| Tapti Bridge | Out of 13, work is in progress on 7 Well foundations |
| Sabarmati Bridge | Geotechnical work completed. Test pile work in progress |
• Stations & Depot:
The works on all 8 HSR Stations from Vapi to Sabarmati are under various stages of construction.
Surat Depot – All 128 foundations have been completed
Sabarmati Depot – Work has been awarded on 4th Feb’22. Earthwork is in progress