NATIONAL HIGH SPEED RAIL CORPORATION LIMITED

नेशनल हाई स्पीड रेल कॉर्पोरेशन लिमिटेड

myth-vs-fact-banners1

तांत्रिक कागदपत्रे

Full Span Box Girders for the Mumbai-Ahmedabad High-Speed Rail Project: Revolution in Fast Pace Construction

By Shri Pradeep Ahirkar, ED/Track & Design
Publication: Journal of Civil Engineering and Architecture, May 2025 Issue

Abstract: The MAHSR (Mumbai-Ahmedabad High Speed Railway) corridor showcased the country’s dream of first HSR (high  speed railway) project and will be a major milestone towards country’s infrastructure development. Globally, more than 20 countries  are already running HSR commercially, Japan has been among the lead players with Shinkansen technology. It has…

Use of the Jack-Down and Pulling Back method for tilt correction in well foundation of the High-Speed Rail (HSR) Narmada bridge

By Shri Akshaya Kumar, Chief Project Manager, NHSRCL

Abstract: Well foundations are one of the oldest, yet most effective foundation types for large-scale Civil structures such as railways, highways, or bridges/viaducts over wide rivers. Though efficient & cost-effective, a usual issue associated with well foundation is the tilting and shifting of wells during the sinking process because of; natural forces such as high river flow and tides and unaccounted soil conditions at the…

Urban Excavation and Environmental Stewardship: Lessons from the Mumbai Station of HSR Project

By Shri Rajneesh Saroj, GM (Civil)/NHSRCL

Abstract:  The Mumbai-Ahmedabad High-Speed Rail project represents a pioneering effort by the Ministry of Railways to introduce high-speed trains in India. Central to this monumental initiative is the construction of the underground station at Mumbai's Bandra Kurla Complex (BKC), a project marked by significant engineering and environmental challenges.

The excavation activities at BKC, located in the heart of the…

Case study on the use of TTHSB bolts in Mumbai-Ahmedabad High Speed Rail Project

By Shri Rajesh Agarwal, Chief Project Manager-III, NHSRCL
Shri Satya Ranjan Acharya, Dy. Chief Project Manager, NHSRCL
Shri Romank Yadav, Jr. Manager, NHSRCL
 

Abstract: Mumbai Ahmedabad High-Speed Rail (MAHSR) project is one of the most ambitious rail projects taken up by GOI. It is aimed to provide better connectivity between two major cities of western India with 12 stops in between. High-speed rail is planned to cater to the upcoming requirement of economic and population…

Forging the future of bridge fabrication: A comparative analysis of Japanese and Indian fabrication techniques with the backdrop of MAHSR project

Shri Rajneesh Saroj, GM/Civil/NHSRCL

This technical paper delves into a comparative analysis of steel bridge fabrication methods employed in Japan and traditional practices in India, with a specific focus on the Mumbai Ahmedabad High- Speed Rail (MAHSR) project’s adaptation of Japanese techniques. Japan’s cutting-edge approach to steel bridge construction, characterized by mechanization, precision, and stringent quality control, is examined in contrast to the conventional methods utilized in India. The…

High Speed Rail Noise Standards and Regulations

 By Shri Sandeep Srivastava, Executive Director (Rolling Stock), NHSRCL
 Shri Govindu Sivasankar, DGM (Rolling Stock), NHSRCL

Abstract : Noise generated by rolling stock in High-Speed Rail (HSR) is of paramount importance from environment point of view. A lot of developments and improvements have happened in rolling stock design to reduce noise during running. There exists different standards and methodology for measurement of noise emanating from running of rolling stock at high-speeds. This paper discusses…

Energy Efficient Operation of Rolling Stock in HSR

By Shri Sandeep Srivastava, Executive Director (Rolling Stock), NHSRCL     

Abstract : Efficiency of high-speed rolling stock and its efficient operation is key to sustainability of any High-Speed Rail (HSR) project. Power/seat is an indicator of energy efficiency of high-speed rolling stock from design point of view. However, energy/seat-km is actual measure of energy efficiency of any high-speed rolling stock and is also referred as HSR efficiency. This paper looks into how the operational techniques combined…

Bridge Articulation and Force Transfer System Mumbai Ahmedabad High-Speed Rail (MAHSR) Corridor

By: Shri D. P. Singh, ED/Design/NHSRCL
Shri Sanjeev Kumar, JGM/Design/NHSRCL
Shri Manoj K Choudary Nalla, DGM/Design/NHSRCL
Shri Rahul Kalra, Sr. Mgr/Design/NHSRCL
Publication: Journal of The Indian National Group of The International Association for Bridge & Structural Engineering

Abstract: Viaducts and Bridges play a pivotal role in transportation infrastructure, serving as critical links between regions and accommodating various modes of transportation,…